Engagement Process & Timelines

Projected Timeline

SSPA/Approval Process

  • Inclusive community outreach (on-going)

  • Approvals of SSPA by Board of Supervisors (12 months)

  • Rezoning + CDP/FDP approval (typically 9-12 months, may be concurrent with SSPA)

  • Engineered site plan and permitting admnistrative provess (12 months)

Construction Timeline

  • At the earliest, construction would be begin 2 to 2.5 years from now (2025)

If you or your community would like schedule a meeting with EYA, please see the “Contact” page